Tuppers Plains-Chester Water District Phase 10 Water System Improvements
Verdantas worked with Tuppers Plains–Chester Water District (TPCWD) to complete their Phase 10 Water System Improvements. TPCWD desired to improve existing water infrastructure within Chester and Bedford townships of Meigs County. The improvements included approximately 45,600 feet of 12, 10” and 8” waterline replacement, a new 250,000-gallon elevated water storage tank and a new above-grade 500 gpm booster station. In addition, the project included system-wide water meter replacement of approximately 5,500 residential and commercial AMR water meters.
Verdantas provided project administration, survey, detailed design, permitting, bidding, construction administration and construction observation services on this nearly $6.8 million project. The project was ranked #18 among Ohio EPA’s Water Supply Revolving Loan Account statewide projects and received 50% of those funds in principal forgiveness with the balance in 0% interest loan. The project also received $250,000 in an Appalachian Regional Commission Grant.
The project involved coordination and permitting with ODOT, Meigs County Engineer and townships for work along and across roadways including US 33.
Project Details:
- Construction completed in 2020
- $6.8 million project cost (over $3.5 million in GRANTS)
- 45,600 LF of 12”, 10” and 8” waterline
- 250,000-gallon elevated water storage
- 500 gpm water booster station
- 5,500 AMR water meters
Services included:
- Survey (topo & lot splits)
- Utility Design including Hydraulics
- Architectural & Electrical (via subs)
- Permitting
- Bidding
- Construction Administration
- Construction Observation
- Funding Assistance
Project Owner
Tuppers Plains-Chester Water DistrictLocation
Reedsville, OhioCapability
Process EngineeringRelated Projects
The City of Bethlehem currently operates a 20-million gallon per day (gpd) activated sludge wastewater treatment plant, which has the ability to handle peak wet weather flows of 50 million gpd.
This project included upgrades to the West Influent Pump Room, which contained three (3) constant speed Yoemens 100 hp dry pit submersible pumps, each with a capacity of 12 MGD. The scope included the replacement of existing pumps along with all piping, valves, and appurtenances located within the West Influent Pump Room. The new pumps were designed to operate on variable frequency drives (VFDs) and controlled on wet well level as monitored by instrumentation. This upgrade also included replacement of the MCCs, and upgrade of the existing control and alarm panels that were integrated into the plant’s existing SCADA system. The scope also included design of a new ventilation system and replacement of existing stairs and platforms.
Our experts leveraged 3D scanning and 3D modeling technology to efficiently design the project. Because space was limited, and all new equipment had to fit within the existing structure, our team scanned the existing facility to develop an accurate as-built the facility, and utilized the scan to develop an accurate 3D model to design the required improvements. The City was able to maintain operation of the treatment plant throughout the duration of the project.
Our team was responsible for all survey, mechanical, electrical, structural and automation design disciplines, preparation of bidding documents, and assisting the City with construction administration services}', 13='{type=image, value=Image{width=745,height=536,url='https://www.verdantas.com/hubfs/Projects/Bethlehem-West-Influent/Bethlehem%201.jpg',altText=''}}', 14='{type=string, value=Leveraging 3D scanning helped develop an accurate 3D model to design the required improvements.}', 15='{type=image, value=Image{width=357,height=243,url='https://www.verdantas.com/hubfs/Projects/Bethlehem-West-Influent/Bethlehem%202.png',altText=''}}', 16='{type=string, value=our team scanned the existing facility to develop an accurate as-built the facility}', 25='{type=number, value=0}', 27='{type=number, value=0}', 29='{type=number, value=16}'}
Precise Visual Technologies | Process Engineering | Mechanical, Electrical, and Automation Engineering
West Influent Pump Replacement
Read about the full service engineering that helped the City of Bethlehem upgrade its activated sludge wastewater treatment plant
With the design and construction of a significant pump station such as Walnut Creek, also comes a sizeable electrical distribution system that is needed to support the large pumps selected for the project. The station design included a 3000Amp, 480/277VAC, switchgear lineup that included primary and alternate source main breaker scheme for transferring between power sources. The lineup included (5) soft-starters, multiple feeder breakers and step down transformers and distribution panels.
Rapid growth in the city of West Des Moines, Iowa resulted in substantial increases in stormwater runoff in most of the community’s watersheds. Such growth made it necessary to mitigate flooding on several major roadways to ensure emergency services were not impacted by closed roadways, as well as to take steps to minimize flooding commercial districts and residential neighborhoods.
Our team worked to provide a comprehensive solution for the City via mitigation solutions including construction of a new 12’ by 5’ reinforced concrete box culvert to intercept and convey interior stormwater flows, and a new 200,000 gallons per minute (gpm) stormwater pump station to discharge runoff to Walnut Creek during elevated flood stages. The stormwater pump station is proposed to be situated along Walnut Creek in an existing U.S. Army Corps of Engineers flood control project – the Des Moines, Iowa levee system. As a result, a U.S. Army Corps of Engineers Section 408 Permit was required for the modifications to the levee.
Hydrologic and hydraulic modeling was completed using XPSWMM 2014 SP1 to evaluate the required total capacity and optimal configuration for the proposed stormwater pump station, to handle both low and high flow precipitation events, using Grand Avenue as the key control elevation to manage flooding in the drainage area. The complex urban drainage area, with multiple collection and conveyance systems, as well as the evaluation taking into account storage in the proposed concrete box culvert, required the sophisticated software package to accurately model the system. The analysis resulted in approximately 200,000 gallons per minute (gpm) of pumping capacity was required to keep interior water elevations to acceptable levels.
The stormwater pump station structure required a complex structural design. A three dimensional analytical model of the pump station was created using finite element analysis. Each component of the structure (walls, slabs, foundations, etc.) was represented by a mesh of 1 ft. x 1 ft. elements that are interconnected to transfer shear, moment, and axial forces. Wall and floor slab thicknesses were computed, floatation stability of the station was determined, and foundation requirements were provided. In addition to the structural design, mechanical design was required for sluice gate intakes to the station, sluice gate outfalls to the Walnut Creek, influent trash racks, and for the pump configuration set points and discharge configuration.
The stormwater pump station was modeled with Revit® software, allowing for 3-dimensional views of the pump station proper and various components. The use of Revit also allowed for continuous updating of quantities of materials as the design progressed, yielding very accurate construction items and quantities for cost estimating. Additionally, considerable attention was given to the visual appearance of the pump station. The use of the Revit modeling software allowed for various architectural treatments to be applied to the views in a rendering fashion, assisting the client in making decisions with respect to the pump station aesthetics.
}', 13='{type=image, value=Image{width=233,height=233,url='https://www.verdantas.com/hubfs/Projects/Walnut-Creek-Stormwater/Walnut%202.jpg',altText=''}}', 15='{type=image, value=Image{width=312,height=312,url='https://www.verdantas.com/hubfs/Projects/Walnut-Creek-Stormwater/Walnut%201.jpg',altText=''}}', 17='{type=image, value=Image{width=1200,height=623,url='https://www.verdantas.com/hubfs/Projects/Walnut-Creek-Stormwater/2015-1580-001-WALNUT%20CREEK%20OUTFALL-CENTRAL-V2015_Page_1-1.jpg',altText=''}}', 25='{type=number, value=0}', 27='{type=number, value=0}', 29='{type=number, value=9}'}
Precise Visual Technologies | Civil Infrastructure | Process Engineering | Mechanical, Electrical, and Automation Engineering | Hydrology, Hydraulics, and Fluids
Walnut Creek Stormwater Outfall and Pump Station
A sizeable electrical distrubution system was needed to support the large pumps selected for this significant pump station