Since 1989, Verdantas ( as Aqua Engineering) has been involved in irrigation and pump system projects for Colorado State University. In addition to the featured project below, our team has provided irrigation engineering services for the following campus facilities:
- College Lake Pump Station Renovation and Upgrade
- Veterinary Teaching Hospital Pump Station Upgrade
- South Campus Pump System and Pond Addition
- Equine Center Irrigation Design, Pond Irrigation and Pumping Concept Plan
- Main Campus Irrigation Improvements
- Foothills Campus Irrigation Improvements
- Lory Student Center Plaza Renovation
- Student Recreation Center Irrigation Services
- Jack Christensen Memorial Track
Featured Project: ARDEC Well and Pump Refurbishment
Our team was contracted to prepare refurbishment construction documents for eight (8) wells at the Agricultural Research, Development and Education Center (ARDEC). Work efforts included:
- Review of all water rights documentation related to each well.
- Existing condition documentation of water rights, well depth, available and required flow
- Well pump demolition
- Defining camera video approach and evaluation
- Defining refurbishment of mechanical treatment, chemical treatment or full well replacement depending on the video findings.
- Preparing bid tabulation sheets so that CSU knew the potential cost of each alternative for each well.
We provided construction period services including operational testing observation.
Solution
Expertise
Geotechnical & Geological Engineering
Water & Wastewater Systems Engineering
Market
Client
Colorado State University
Location
Fort Collins, CO