After vessel impacts damaged timber fender piles at a marine terminal in Seattle, approximately 20 linear feet of the berth could no longer be used for vessel operations. Repairs were needed to restore the affected area while meeting environmental requirements associated with in-water construction.
The work included removing damaged timber fender piles and replacing them with 14-inch steel piles, along with replacing HDPE chafing plates, reconnecting the new piles to the existing pile caps, and replacing additional missing fender piles.
Verdantas led environmental permitting at the federal, state, and local levels, along with environmental review and agency coordination to support the repair work. This included navigating requirements associated with in-water construction and coordinating environmental considerations as the project moved toward construction.
During construction, Verdantas also provided marine mammal monitoring to support compliance with NOAA Fisheries requirements and minimize potential impacts to protected species. Monitoring focused on species protected under the Endangered Species Act, including humpback whales, Southern Resident killer whales, and Steller sea lions.
Over three days of pile-driving activities, Verdantas monitored the action area and surrounding waters. Procedures were in place to stop work if a protected species entered the designated area. No ESA-listed marine mammals were observed during monitoring, while harbor seals observed in the vicinity showed no signs of disturbance associated with pile driving or surrounding construction activities.
By incorporating environmental monitoring into the repair work, the project was able to move forward with safeguards in place for protected species while meeting applicable regulatory requirements. The completed repairs restored the damaged portion of the berth, supporting its return to reliable vessel operations.